Font size:
+A
-A
Mode:
Return to the normal mode
Switch to the mode for the visually impaired
Rozhkov Development

Rozhkov Development
Location
West Kazakhstan region
Terms of implementation
2019-2024
Participants
JSC NC «KazMunayGas» – 50%, MOL (FED) Kazakhstan – 27.5%, First International Oil Corporation (FIOC) – 22.5% participation share.
Current status
The field was commissioned in December 2023. Work on further expansion is in progress.
Key indicators
  • 15
    recoverable condensate, million tons
  • 33
    gas-in-place, billion m3
  • 141.7
    investment, million US dollars
  • 101
    new jobs during the construction period
  • 110
    new jobs during operation
  • 29
    dry gas, billion m3
The project is to increase the resource base under Contract No. 4130-УВС-МЭ for gas and condensate production at the Rozhkov field dd 02 Apr 2015. The Rozhkov gas and condensate field was discovered in 2008.
 The field is at the stage of development and preparation. Commissioning is planned by the end of 2023.

The project provides for:

•Onshore facilities construction for cooperation with Zhaiykmunai LLP (Nostrum Oil & Gas Plc);

•Completion (re-entry) of previously drilled 8 wells.

Press-releases
All news